The Lycoming XR-7755
Contracts/Administrative Chronology, 1946
by Kimble D. McCutcheon
9 Jun 1946. Supplemental Agreement No. 7 (S-16919) to Supplies Contract No. W 33-038 ac-564 (11169); AFP 421265; Contractor – The Aviation Corporation (Lycoming Division); Supplemental Agreement For: Additional Development Work
Change in Estimated Cost: Increase = $859,549.04; Change in Fixed Fee: Increase = $34,381.96
The parties agree as follows:
First: Item 12 Exhibit 1 is amended as follows:
(a) In addition to the work called for under Item 12-2, Lycoming shall perform the following:
Necessary redesign, parts and testing required for 2,500 hrs of additional endurance testing of one-, three- or four-cylinder engines as a continuation of the work called for under Item 12-2, Exhibit 1 to Item 12, but excluding short-stroke running and the option contained in paragraph (f) of Article 1 of the Supplies Contract. At least 500 hrs shall be at or above takeoff power and speed; 500 hrs at best economy cruising conditions; the remaining 1,000 hrs shall be at or above minimum cruising. All ratings related to such testing shall be as defined in Item 12-5 of the supplies contract. Three report copies were to be furnished.
(b) In addition to the work called under Item 12-4, Lycoming shall perform the following:
Necessary redesign, parts and testing required for 2,500 hrs of additional performance and calibration testing of one-, three- and four-cylinder engines a continuance of the work called for under Item 12-4. At least 250 hrs shall be run at or above normal power and speed; the remaining 2,250 hrs shall be at or above minimum cruising. All ratings related to such testing shall be as defined in Item 12-5. Three report copies were to be furnished.
Second: Supply Contract Statement of Work Article 1 is amended as follows:
(a) By adding after Item 12 of paragraph (a) thereof the following new items:
Item 13 – Necessary redesign, parts, assembly and 500 hrs testing required to accomplish a 50-hr nose-to-nose endurance test of the two Government-loaned reduction gear units, manufactured under Item 12-10, and a shifting test without a major failure or other major unsatisfactory condition of any of the reduction gear components. The conditions of such tests shall be established by mutual agreement between Lycoming and the PPL. Three report copies were to be furnished.
Item 14 – Necessary redesign, parts and 400 hrs of testing to include a satisfactory 50-r development test on an XR-7755-1 or XR-7755-5 engine built under Item 12-11. Such development test shall be conducted in accordance with Army Air Corps Specification No. 28144-A dated 25 Aug 1939, with the exception that the requirements of Paragraph F-6c thereof shall be omitted and any other omissions and/or exceptions as may b necessary providing such omissions and/or exceptions have been agreed upon between Lycoming and the Government. After successfully completing the 50-hr test, the remainder of the test hours of this item, if any, shall be conducted in a manner agreed upon between Lycoming an the PPL Chief. A propeller suitable for use during the running of these tests shall be loaned by the Government. Three report copies were to be furnished.
Item 15 – Build one XR-7755-3 engine in accordance with the requirements of Lycoming Specification No. 2031-A, dated 4 Jun 1945 with such modifications thereto as may be agreed upon between Lycoming and the PPL Chief, using the parts produced under Item 12-8 and one reduction gear unit assembled under Item 13. Provide the necessary redesign, parts and testing required for 100 hrs testing to include a 50-hr development test on the XR-7755-3 without a major failure or other major unsatisfactory condition if the testing time permits. Such test shall be conducted according to the following schedule:
- Five hours at approximately 1,300 rpm and 89 bmep with 0.354 reduction gear ratio and best economy fuel-air ratio.
- Five hours at approximately 1,600 rpm and 125 bmep with 0.354 reduction gear ratio and best economy fuel-air ratio.
- Ten hours at approximately 1,900 rpm and 135 bmep with 0.354 reduction gear ratio and best economy fuel-air ratio.
- Ten hours at approximately 2,200 rpm and 139 bmep with 0.246 reduction gear ratio and best economy fuel-air ratio.
- Ten hours at approximately 2,300 rpm and 178 bmep with 0.246 reduction gear ratio and best economy fuel-air ratio.
- Ten hours in accordance with a reduction gear ratio shift cycle as mutually agreed upon between Lycoming and the PPL Chief.
Any remaining test hours of this item shall be conducted in a manner agreed upon between Lycoming and PPL Chief prior to running the hours. Suitable propellers for running the aforementioned tests shall be loaned by the Government. Three report copies were to be furnished.
Item 16 – Necessary redesign, parts and testing required for 100 hours performance testing on an XR-7755-1, XR-7755-3 or XR-7755-5 engine built under Item 12-11 or Item 15 of this contract. Insofar as the testing time permits tests shall include the following:
- Torsional vibration checks.
- Tests to determine optimum spark, valve and fuel injection timing
- Heat rejection to coolant and oil.
- Calibration.
- Air-fuel distribution investigation.
- Manifolding.
- Comparison of fuel injection versus carburetion.
- Supercharging.
- Spark plug performance.
- Other tests approved by the PPL.
Three report copies were to be furnished.
(b) By adding after paragraph (g) thereof the following new paragraph:
- (h) It is anticipated that the Government will lend Lycoming two reduction gear units manufactured under Item 12-10 for the nose-to-nose endurance test as provided in Item 13 of paragraph (a) hereof,
- (ii) a propeller suitable for use during the running of the tests provided in Item 14 of paragraph (a),
- (iii) suitable propellers for running the tests provided in Item 15 of paragraph (a) hereof.
Third: Article 2 – Estimated Costs of the Supplies Contract is amended and supplemented as follows:
- (a) by deleting the fifteenth line thereof and by substituting the following under the headings "Item" and "Estimated Costs" respectively:
| Item | Cost |
| 12 | $2,354,951.92 |
| 13 | $96,600.00 |
| 14 | $271,997.12 |
| 15 | $68,000.00 |
| 16 | $68,000.00 |
- (b) The total estimated cost of Exhibit 1 Item 12-2 was increased by $177,475.96 and the total estimated cost of Item 12-4 was increased by $187,475.96.
Forth: Article 3 – Consideration – of the Supplies Contract is amended and supplemented as follows:
(a) By deleting the first sentence of paragraph (a) subparagraph (1) thereof and by substituting therefore the following:
"(1) In addition the Government will pay the Contractor for work performed pursuant to Item 12 of Article 1(a) hereof a fixed fee of four per cent (4%) of the estimated cost st forth in all Exhibits approved and attached hereto and made a part hereof as provided in said Item 12 and as said Exhibits may be amended by Supplemental Agreement or Change Orders hereto. Further, that Government will pay the Contractor for work performed pursuant to Items 13 to 16 inclusive of Article 1(a) hereof a fixed fee of Twenty Thousand One Hundred Eighty Three Dollars and Eighty-Eight Cents ($20,183.88)(being 4% of the estimated cost of Five Hundred Four Thousand Five Hundred Ninety-Seven Dollars and Twelve Cents ($504,597.12) for said Items 13 to 16 inclusive)."
(b) By adding a new subparagraph (5) to paragraph (b) thereof:
"(5) Costs of overtime wage payments subsequent to 1 Sep 1945, shall be allowable at lower of the costs hereunder only as and to the extent that the overtime work for which payments are made shall have been expressly authorized in writing by the Contracting Officer propr to the performance of such work."
Fifth: Article 4 – Delivery – of the Supplies Contract is amended and supplemented as follows:
- (a) The additional work and material called for under paragraph (a) of Section First, hereof shall be delivered on or before 1 Aug 1946.
- (b) The additional work and material called for under paragraph (b) of Section First, hereof shall be delivered before 1 Jan 1947.
- (c) By adding under the respective headings the following items and delivery schedules thereof:
| Item | Delivery |
| 13 | 1 Jan 1947 |
| 14 | 1 Jan 1947 |
| 15 | 1 Jan 1947 |
| 16 | 15 Nov 1946 |
Sixth: Article 6 of the Supplies Contract is hereby amended by increasing the total sum allotted for this contract, referred to in paragraph (c) of said Article, by Eight Hundred Ninety-Three Thousand Nine Hundred Thirty-One Dollars ($893,931.00).
Seventh: This Supplemental Agreement in the formal contract contemplated by Supplement to Letter Contract addressed by the War Department to the Contractor under date of 26 Nov 1945, and this Supplemental Agreement, this Supplemental Agreement shall govern.
Eighth: The provisions of the Vinson-Trammel Act (which placed limits on profits for war materiel) for the following reasons:
- (a) The procurement made under the terms of this Supplemental Agreement is not a ndw one made subsequent to 31 Dec 1945 and constitutes merely a formalization of a valid contract entered into prior to 1 Jan 1946, viz. The Letter Contract mention in section Seventh hereof, and
- (b) The supplies called for herein do not constitute complete aircraft or any portion thereof.
Ninth: Nothing herein contained shall be deemed to require the Contractor to manufacture, furnish or deliver any articles or supplies, or to perform any work, as to which a Notice of Termination is in effect at the effective date hereof, nor to require the Government to accept any such articles, supplies or work; and any such new Notice of Termination shall be applicable, to the extent stated therein, to any articles, supplies or work calling for hereby or otherwise referred to herein.
Tenth: Except as hereby modified either expressly or by necessary implication all of the terms covenants and conditions of the Supplies Contract shall continue in full force and effect and shall apply to the articles and supplies to be furnished hereunder.
Eleventh: This Supplemental Agreement shall be subject to the written approval of the Secretary of War or such individual as said Secretary may designate and shall not be binding until so approved. [RG 342 RD2311. XR-7755 Contract W-33-038AC-564. Supplement Agreements, CCNs, Change Orders]
3 Sep 1946. R.E. Posthauer, Lycoming's Manager Military Contracts, wrote the ATSC requesting that Contract W 33-038 ac-564 Item 12-5 Change Order No. 8 to the Contract version dated 8 Aug 1946 be rewritten as follows:
A. Item 12-5, listed under Exhibit "1" to Item 12 as amended, is hereby revised as follows at no change in estimated cost and fixed fee:
- (1) That part of the third line of paragraph 1 reading "based on a normal multi-cylinder engine rating of 4,000 hp at 2,300 rpm and 205 imep, and a takeoff rating of 5,000 hp at 2,600 rpm and 231 imep, with the following exception: " is hereby deleted and made of no further effect and in lieu thereof the following is hereby substituted: "based on a normal multi-cylinder engine rating of 5,000 bhp at 2,500 rpm and 241 imep and a takeoff rating of 6,000 bhp at 2,800 rpm and 264 imep with the following exceptions:"
- (2) Paragraph 6 reading "In this test the engine 1…"is hereby amended by removing the colon appearing at the end and by substituting in lieu thereof the following: "and future single cylinder tests specified under Items 1 and 2 of Supplement No. 1 dated 26 Nov 1945".
- (3) The performance table appearing at the end of said Item 12-5 is hereby deleted and made of no further effect and in lieu thereof the following table is hereby submitted:
| Single Cylinder Performance | Engine Performance |
| Rating | imep (psi) | Guaranteed isfc (lb/ihp/hr) | Spark Advance (°) | bhp | rpm | bmep (psi) | bsfc (lb/bhp/hr) | Mechanical Efficiency |
| Takeoff and Military | 264 | 0.58 | 12 | 6,000 | 2,800 | 219 | 0.70 | 0.83 |
| Normal | 241 | 0.52 | 12 | 5,000 | 2,500 | 205 | 0.61 | 0.85 |
| High Cruise | 155 | 0.35 | 22 | 3,000 | 2,200 | 139 | 0.39 | 0.90 |
| Med Cruise | 143 | 0.333 | 22 | 2,000 | 1,600 | 128 | 0.37 | 0.90 |
| Low Cruise | 90 | 0.34 | 22 | 1,000 | 1,300 | 79 | 0.39 | 0.88 |
17 Sep 1946. Power Plant Laboratory Chief Col R.J. Minty accepted Change Order No. 8 except that the last paragraph should have read, "…and future single cylinder tests specified under Items 1 and 2 of Supplement No. 7, approval now pending." [RG 342 RD 2311 XR-7755 Contract W-33-038AC-564 Authorizing Correspondence. 012-014.]
In the weeks prior to the 11 Sep 1946 conference between AMC and Lycoming at Wright Field, Blackwood, in a series of undated hand-written notes, appears to be preparing what would become Lycoming AFP 14587. This anticipated further contract calls prior to 30 Jun 1947 that would cover more turbine compounding development work, and included draft purchase request No. 14585, marked later cancelled. Also included was a working Exhibit A, scope of work to the above AFP, along with more hand-written preparatory notes and more draft AFP No. 14585 attachments. [RG 342 RD2311. XR-7755 Contract W-33-038 ac-564. Proposed Procurement and Mods. 001-005.]
The corresponding
EO 503-602 Addendum 3 scope of work included:
- (a) Building of an XR-7755-1 or XR-7755-5 engine.
- (b) Providing a set of spare parts set for an XR-7755-7 plus additional parts to convert the engine of Item (a) above to an XR-7755-7 engine.
- (c) 500 hrs of XR-7755 single-cylinder performance running for performance analysis and predictions of expected multi-cylinder turbine compounded engine performance and reports of such running.
- (d) Studies to determine potential maximum power and fuel economy of a compounded multi-cylinder XR-7755 engine based on the results of tests performed under Item (a) above and reports of such studies.
- (e) 700 hrs XR-7755 single-cylinder endurance running at ratings as determined from Item (a) above and reports of this running.
- (f) Engineering studies, design and blueprints of the XR-7755 engine adapted for turbine compounding.
- (g) Extension of XR-7755 engine turbine compounding initiated in the above items.
Estimated ATSC labor cost for this activity was previously estimated at $4,500.00; new estimate was $7,000.00. Previous estimate of Lycoming's work was $4,545,506.00; new estimate was $5,945,506.00. Total previous estimate was $4,550,006.00; new estimate was $5,952,506.00. Signed by Blackwood and Col Minty, PPL Chief.
At some point, PPL Chief Col Minty advised Blackwood, Chenoweth, and E.O. Wolfe that the project would be cancelled or restructured. The objective had switched to a 50-hr flight test and making an engine available for that test, which if successful, might result in the contract being reopened later. This led Blackwood to prepare undated contract status notes and tasks to be accomplished in connection with the contract cancellation/restructuring:
- Stop 4-cylinder work now.
- Complete Items 10 and 11.
- Item 8 = ?
- Item 12-6. Find Item 8 ratio of expenditure ($13,300.00 per month) and get Lycoming richer on this ($3,100 per month).
- Continue 12-8.
- Stop 12-9.
- Permit parts to come through 12-10 but no testing.
- Item 12-11 = OK.
- Item 12-12 = Cancel.
- Supplement #7 Item 3 = Cancel.
- Supplement #7 Item 2 = Drop.
- Supplement #7 Item 4 = Keep.
- Substitute 50-hr flight test for Spec 28144 (modified rating if found necessary or start lower).
- Defer Supplement #7 Item 5.
- Cancel Supplement #7 Item 6.
[RG 342 RD2311. XR-7755 Contract W-33-038 ac-564. Proposed Procurement and Mods. 013-]
26 Sep 1946. R.E. Posthauer, Lycoming's Military Contracts Manager, wrote the PPL covering an 11 Sep 1946 conference at Wright Field, which had included Cols Minty, Wassel and O'Keefe, and Messrs. Berger and Blackwood; Posthauer and Carpenter had attended on behalf of Lycoming.
1. Lycoming produced a proposal in compliance with the conclusions reached.
2. The proposal consisted of the following items:
- (a) Necessary design, parts, tools, jigs, fixtures, special instrumentation and testing to accomplish 500 hrs performance running of a single XR-7755 cylinder. This testing was to obtain data on compression ratio, valve timing, spark timing, exhaust back pressure, fuel and detonation suppression methods. This data would be used for performance analysis and predictions of expected multi-cylinder compounded engine performance. The scope of variable investigation shall be determined as tests progress but shall not exceed 500 hrs. Three report copies shall be submitted. Delivery = 5 mo after contract; Cost without fee = $26,450.00.
- (b) Studies to determine potential maximum power and fuel economy of a compounded, multi-cylinder XR-7755 engine. These studies are to be based on the results obtained under Item (a) and such other pertinent data as may be available. In the event of a contract, the Contractor requests the Government to make available all information necessary for the Contractor to make an adequate study. Three report copies shall be submitted. Delivery = 8 months after contract; Cost without fee = $7,303.00.
- (c) Necessary design, parts, tools, jigs, fixtures, special instrumentation and testing of a single XR-7755 cylinder at cruise power, normal rated power, takeoff and military power as determined from Item (a). Three report copies shall be submitted. Delivery = 13 months after contract; Cost = $37,134.00.
- (d) Engineering design, layout and detail work covering initial design of the XR-7755 engine adapted for compounding. Assembly and detail drawing blueprints in triplicate shall be submitted. Delivery = 11 months after contract; Cost = $126,063.00.
- (e) Design, parts, procurement and test.
- 1. Engineering design, layout and detail work covering design of the feedback turbine drive, turbines, main and auxiliary stage supercharger, controls, intercoolers, and ducting necessary for compounding the multi-cylinder XR-7755 engine. Assembly and detail drawing blueprints in triplicate shall be submitted.
- 2. Procure sufficient parts for 2 complete units, plus spare turbine and compressor rotors.
- 3. Necessary design, tools, jigs, fixtures, special instrumentation to build and conduct independent tests on components. Tests to be conducted on the following:
- a) Main stage supercharger
- b) Auxiliary stage supercharger
- c) Feedback turbine
- d) Compressor turbine
- e) Feedback turbine drive
- f) And such other tests as are approved by the PPL
Three report copies shall be submitted. Delivery = 26 months after contract; Cost = $588,420.00. Lycoming requested a 4% fee on all above items.
3. The subject of 4-cylinder testing was studied in some detail by the Contractor. The Contractor's conclusions were that it would be more advantageous and of more benefit to the Government to first accomplish the 1-cylinder testing as outlined in 2(c) above and then proceed with 4-cylinder testing if conditions indicated that this was necessary. The reasons for this are as follows:
- (a) The intake manifold pressure and exhaust back pressure to simulate the compounded XR-7755 engine are not known, and cannot be known until 1-cylinder performance work has been accomplished. However, it is expected that the intake manifold pressure will be on the order of 70 – 80 inHgA, which is beyond the capacity of the present supercharger or shop air system. As soon as required conditions are known as a result of 1-cylinder work, a decision on 4-cylinder engine procedure and equipment can be made.
- (b) About 700 hrs of 1-cylinder engine endurance operation are requested in order to properly evaluate and develop the cylinder head, exhaust valve and guide under controlled conditions; also it is believed that this can be done more expeditiously with a 1-cylinder engine due to much less assembly and setup time. It is believed that the final evaluation, i.e., checking the effect of 4-cylinder exhaust and intake manifolds, can be adequately accomplished (prior to full-scale XR-7755 engine tests) with 300 hrs of 4-cylinder engine operation.
4. Lycoming suggested, in view of the above that 4-cylinder work be put in the nature of a call to the subject contract. The contractor's proposal on this item is as follows: Necessary design, parts, tools, Jigs, fixtures, special instrumentation and testing to accomplish 300 hrs of endurance testing of a 4-cylinder in-line XR-7755 engine at condition based on information obtained from Items (a) and (c); these conditions to be agreed upon by the AMC and the Contractor. Three reports shall be submitted. Delivery = 12 months after contract; Cost = $172,530.00. [RG 342 RD2311. XR-7755 Contract W-33-038 ac-564. Proposed Procurement and Mods. 460926019-022]
23 Oct 1946. R.E. Posthaur, Lycoming's Military Contracts Manager, sent quotations to the AMC, responding to a verbal request:
- (a) Build one XR-7755-1 or XR-7755-5 engine using the parts set provided in Contract W-33-038 ac-564 Item 12-9. Delivery = 15 months after contract; Cost without fee = $16,000.00.
- (b) Provide one complete parts set as required for one XR-7755-3 engine except that fuel injection will be provided, and one additional reduction gear parts set necessary to convert the engine in Item (a) above to an XR-7755-3 engine with fuel injection. Delivery = 20 months after contract; Cost without fee = $490,000.00.
A fixed fee of 4% should be added to the above. [RG 342 RD2311. XR-7755 Contract W-33-038 ac-564. Proposed Procurement and Mods. 461023018.]
25 Oct 1946. Posthauer sent updated quotations, superseding those sent on 23 Oct 1946, with these revised quotes:
- (a) Build one XR-7755-1 engine in accordance with Lycoming Specification No. 2020-C dated 4 Jun 1945, or one SR-7755-5 engine in accordance with Lycoming Specification No. 2040-A dated 29 Nov 1945; such model specification to have modifications thereto as the Contractor and PPL may agree upon. The aforementioned engine shall be built using the parts set provided in Contract W-33-038 ac-564 Call No. 1 Item 12-9. Delivery =15 months after contract; Cost without fee = $16,000.00. To the above a 4% fixed fee should be added.
- (b) One finished parts set for an XR-7755-7 engine in accordance with Lycoming Specification No 2031-A dated 4 Jun 1945, except fuel injection shall be provided in lieu of carburetion. One additional parts set as required for dual-rotation two-speed reduction gear front end.
One additional set of fuel injection equipment. The parts of the second and third paragraphs of Item (b) shall be built such that the engine of Item (a) hereof may be converted to an XR-7755-7 engine by installation of such parts. Delivery = 20 months after contract; Cost without fee = 490,000.00. To the above a 4% fixed fee should be added. [RG 342 RD2311. XR-7755 Contract W-33-038 ac-564. Proposed Procurement and Mods. 461025016-017.]
13 Nov 1946. Expenditure Order 503-602 Addendum 3, originated by Blackwood, was approved by PPL Chief Col R.J. Minty and Engineering Division Chief Maj Gen L.G. Craigie. This amended EO 503-602 to extend Call Contract W-533-038 ac-564 by $1,400,000.00 for the XR-7755 aircraft engine. Contract Calls were anticipated to cover the following:
- (a) Building of an XR-7755-1 or XR-7755-5 engine.
- (b) Providing a spare parts set for an XR-7755-7 engine plus additional parts to convert the engine from (a) above to an XR-7755-7 engine.
- (c) 500 hrs performance running of an XR-7755 single cylinder for performance analysis and for predictions of expected multi-cylinder turbine compounded engine performance and reports os such running.
- (d) Studies to determine potential maximum power and fuel economy for a compound multi-cylinder XR-7755 engine and reports on such studies.
- (f) Engineering studies, design and blueprints of the XR-7755 engine adapted for turbine compounding.
- (g) Extension of the XR-7755 engine turbine compounding development initiated in the above items.
This contract amendment would increase the ATSC labor from $4,500.00 to $7,000.00. Outside purchases would increase from $4,545,506.00 to $5,945,506.00 and the total expenditure would increase from $4,550,006.00 to $5,953,506.00. [RG 342 RD2311. XR-7755\XR-7755 Contract W-33-038AC-564, Contract Calls. 461113034-035.]
27 Dec 1946. Blackwood produced a hand-written budget approximation after the project budget was cut from $1,400,000.00 to around $400,000.00.
| Activity | Cost |
| Single-Cylinder Performance Running | $26,450.00 |
| Studies | $7,303.00 |
| Single-Cylinder Endurance Running | $37,134.00 |
| XR-7755 Design, Layout and Modification | $126,063.00 |
| Design of Feedback Turbine,etc. | $150,000.00 |
| | =========== |
| Total | $346,950.00 |
[RG 342 RD2311. XR-7755 Contract W-33-038 ac-564. Proposed Procurement and Mods. 461227023.]